April 18, 2007 – Approval of Project Initiation Request by Academic Planning Committee
April 24, 2007 – Program Statement to UNCA
June 14, 2007 – Board of Regents approves Program Statement
July 19, 2007 – CCPE review
September 6, 2007 - Architect selection approval by Board of Regents
September 10, 2007 – Start design
July 10, 2008 – Complete design
July 11, 2008 – Project out for bid
September 13, 2008 – Award construction contract
September 14, 2008 – Start construction
August 16, 2009 – Complete construction
August 20 and 21 - Open House from 7 a.m. to 6 p.m. Parents please bring your children to see the center.
August 24 - First Day of care at the center.